The project sponsor advises the project manager that there has been a change in the organizational structure. What should the project manager do next?
A、Inform the sponsor that it will cost more to make changes
B、Request that the sponsor conform to the integrated change control process
C、Update the communications plan to reflect the new structure
D、Organize a meeting with the new stakeholder group