午夜无码中文字幕影院,国产自产第一区c国产,久久久久久夜精品精品免费,国产99久久,夜夜夜夜曰天天天天拍国产,欧美日韩亚洲另类专区,国产精品区一区二区免费

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容



The project manager has recently been appointed to an ongoing software development project. The stakeholder considers that the project is on schedule and budget according to the previous project manager’s reports. During the new project manager reads the relevant project’s documents, he knows the project schedule delay and over budget. What the project manager should do?
A、Efforts to fast track the progress of the project in order to meet demand
B、 Report to stakeholders to assess the situation
C、 Use of existing resources to continue to run the project
D、 Meeting with stakeholders and apply more resources


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容