午夜无码中文字幕影院,国产自产第一区c国产,久久久久久夜精品精品免费,国产99久久,夜夜夜夜曰天天天天拍国产,欧美日韩亚洲另类专区,国产精品区一区二区免费

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
當(dāng)前位置:信管網(wǎng) >> 在線考試中心 >> 信息安全工程師題庫(kù) >> 試題查看
試卷名稱 信息安全工程師英語(yǔ)試題匯總
考試中心《信息安全工程師英語(yǔ)試題匯總》在線考試
試卷年份2016年下半年
試題題型【單選題】
試題內(nèi)容

When reviewing a project where quality is a major concern, an IS auditor should use the project management triangle to explain that: 
A、increases in quality can be achieved, even if resource allocation is decreased. 
B、increases in quality are only achieved if resource allocation is increased. 
C、decreases in delivery time can be achieved, even if resource allocation is decreased. 
D、decreases in delivery time can only be achieved if quality is decreased. 


相關(guān)試題

推薦文章