PMP?當天每日一練試題地址:m.xomuzic.com/exam/ExamDay.aspx?t1=33
往期PMP?每日一練試題匯總:m.xomuzic.com/class/27/e33_1.html
PMP?每日一練試題(2022/12/30)在線測試:m.xomuzic.com/exam/ExamDay.aspx?t1=33&day=2022/12/30
點擊查看:更多PMP?習題與指導
PMP?每日一練試題內容(2022/12/30)
試題1
項目經理決定采用一個主動接受戰(zhàn)略管理特定風險。項目經理接下來應該怎么做?()查看答案
試題參考答案:B
試題解析與討論:m.xomuzic.com/st/4913418608.html
試題2
項目發(fā)起人識別到,項目支出大大超出原計劃,項目發(fā)起人詢問項目經理還需要多少資金才能最終完成項目,項目經理應該使用什么來評估這個問題?查看答案
試題參考答案:D
試題解析與討論:m.xomuzic.com/st/461904442.html
試題3
A product manager suggests design changes to add product value when compared with competitive products. These changes will benefit the company,but involve extra activities. What should the project manager do?查看答案
試題參考答案:B
試題解析與討論:m.xomuzic.com/st/4804829321.html
試題4
在項目中,產品愿景將會驅動哪一個組件交付:查看答案
試題參考答案:A
試題解析與討論:m.xomuzic.com/st/4250916323.html
試題5
公司決定為一個新項目實施敏捷,并成立一個敏捷團隊。為確保成功,應如何組織敏捷團隊?查看答案
試題參考答案:B
試題解析與討論:m.xomuzic.com/st/5306588.html
試題6
During a demonstration, the customer provides feedback and requests a new;urgent enhancement due to a regulation change. What should the agile project manager do next?查看答案
試題參考答案:C
試題解析與討論:m.xomuzic.com/st/4766718314.html
試題7
During project closure.the project manager finds it difficult t o obtain successful project completion feedback. Some stake holders disagree with the project's success criteria and have been frustrated with the project from the beginning. To what should the project manager refer to address these concerns?在項目收尾期間.項目經理發(fā)現很難得到關于項目成功完成的反饋.一些相關方對項目的成功標準意見不一致.并從一開始就對項目感到沮喪。 項目經理應查閱下列哪一份文件來解決這些問題?查看答案
試題參考答案:C
試題解析與討論:m.xomuzic.com/st/4802822935.html
試題8
A project manager is leading a project to develop a new company-sponsored community event. There are several competing priorities and significant logical details. Since security is t he top priority,the project team contracts a security subject matter expert(SME).Together they create a risk matrix and discover that the overall risk level is lower than expected.Why was the overall risk score lower than expected?查看答案
試題參考答案:A
試題解析與討論:m.xomuzic.com/st/477588581.html
試題9
After receiving a project management office(PMO)mandate that work packages must be performed by a preapproved offshore unit,the project manager updates the risk register. T o mitigate the risk of miscommunication between local and offshore teams,the project manager appoints an offshore coordinator as a single point of contact. What plan should be updated to describe the interactions between the two teams?在收到項目管理辦公室(PMO)規(guī)定工作包必須由一家預先批準的海外單位執(zhí)行后,項目經理更新了風險登記冊,為了減輕本地和海外團隊之間溝通不暢的的風險,項目經理任命一名海外協調員作為單一聯絡點.應該更新哪項計劃來描述兩個團隊之間的互動?查看答案
試題參考答案:D
試題解析與討論:m.xomuzic.com/st/478548350.html
試題10
敏捷管理專業(yè)人士建議使用一些過程改進技術,但該技術導致速度降低并產生了一些質量問題。團隊已經進行修正,但是職能經理很不高興,此時應該怎么做會避免這樣的結果?查看答案
試題參考答案:B
試題解析與討論:m.xomuzic.com/st/5296426926.html
信管網訂閱號
信管網視頻號
信管網抖音號
溫馨提示:因考試政策、內容不斷變化與調整,信管網網站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!