PMP?每日一練試題(2022/12/22)

PMP?當(dāng)天每日一練試題地址:m.xomuzic.com/exam/ExamDay.aspx?t1=33

往期PMP?每日一練試題匯總:m.xomuzic.com/class/27/e33_1.html

PMP?每日一練試題(2022/12/22)在線測(cè)試:m.xomuzic.com/exam/ExamDay.aspx?t1=33&day=2022/12/22

點(diǎn)擊查看:更多PMP?習(xí)題與指導(dǎo)

PMP?每日一練試題內(nèi)容(2022/12/22)

  • 試題1

    The project manager is developing a schedule for a communications project. The available project information is vague. What should a project manager do to address this?
    A.Increase the total float of all activities.
    B.Determine activity durations using three-point estimating. 
    C.Assign a contingency reserve for uncertain activities. 
    D. Meet with the project team to estimate activity durations. 
    項(xiàng)目經(jīng)理正在為一個(gè)溝通項(xiàng)目制定一份進(jìn)度計(jì)劃。可用的項(xiàng)目信息很模糊。若要解決這個(gè)問題,項(xiàng)目經(jīng)理應(yīng)該怎么做?
    A、增加所有活動(dòng)的總浮動(dòng)時(shí)間。
    B、使用三點(diǎn)估算確定活動(dòng)持續(xù)時(shí)間。
    C、為不確定的活動(dòng)分配應(yīng)急儲(chǔ)備。
    D、與項(xiàng)目團(tuán)隊(duì)一起開會(huì),估算活動(dòng)持續(xù)時(shí)間。

    查看答案

    試題參考答案:D

    試題解析與討論:m.xomuzic.com/st/497879519.html

  • 試題2

    你是公司某敏捷項(xiàng)目的Scrum Master。在有一天的每日站會(huì)上,某成員提出了一個(gè)問題,他正在同時(shí)處理6個(gè)故事,這讓他非常不知所措。請(qǐng)問,對(duì)于在制品(Work in Process),如果不加以限制,團(tuán)隊(duì)最有可能出現(xiàn)下面哪一種情景?
    A.不會(huì)影響團(tuán)隊(duì)的狀態(tài),一切都能順利進(jìn)行; 
    B.會(huì)出現(xiàn)資源不飽和的情況; 
    C.每個(gè)人都會(huì)很忙,但是沒有瓶頸; 
    D.每個(gè)人都會(huì)很忙,但是不知道瓶頸在哪。

    查看答案

    試題參考答案:D

    試題解析與討論:m.xomuzic.com/st/5268513621.html

  • 試題3

    公司的軟件項(xiàng)目已經(jīng)完成框架搭建,進(jìn)入后期功能實(shí)現(xiàn)階段,團(tuán)隊(duì)使用燃盡圖查看了項(xiàng)目完成情況,發(fā)現(xiàn)框架搭建超過預(yù)期時(shí)間,導(dǎo)致功能的交付成日期將延遲5天時(shí)間。 捷管理專業(yè)人士,你應(yīng)該怎樣幫助團(tuán)隊(duì)解決這個(gè)問題?
    A.在即將到交付日期的時(shí)候和客戶解釋這個(gè)情況 
    B.要求敏捷教練減少產(chǎn)品功能,保證按期交付 
    C.聯(lián)系PO以及各相關(guān)方一起討論協(xié)商延長(zhǎng)交付時(shí)間或者減少功能 
    D.要求團(tuán)隊(duì)后續(xù)加班,以保證交付

    查看答案

    試題參考答案:C

    試題解析與討論:m.xomuzic.com/st/5266329306.html

  • 試題4

    通常用貨幣單位來表示項(xiàng)目成本,但有時(shí)候也可能采用非貨幣形式來表示,以便:
    A、提高成本估算的準(zhǔn)確性
    B、消除通貨膨脹的影響,便于成本比較
    C、估算項(xiàng)目活動(dòng)的直接成本
    D、估算項(xiàng)目活動(dòng)的人工費(fèi)

    查看答案

    試題參考答案:C

    試題解析與討論:m.xomuzic.com/st/425483116.html

  • 試題5

    你正在管理一個(gè)公共項(xiàng)目。該項(xiàng)目牽涉所在城市所有居民的利益,是當(dāng)?shù)孛襟w和居民關(guān)注的熱點(diǎn)。他們想要了解項(xiàng)目的一切情況。針對(duì)這種情況,你會(huì)使用哪種溝通方法來發(fā)布項(xiàng)目的工作績(jī)效信息和工作績(jī)效報(bào)告?()
    A.推式溝通
    B.拉式溝通
    C.互動(dòng)溝通
    D.書面溝通

    查看答案

    試題參考答案:B

    試題解析與討論:m.xomuzic.com/st/493338172.html

  • 試題6

    項(xiàng)目經(jīng)理通過資格預(yù)審,確定了由7個(gè)廠家組成的合格賣方清單。已經(jīng)向他們發(fā)出了招標(biāo)文件,要求他們提交詳細(xì)、全面的投標(biāo)文件,并將組織專家進(jìn)行評(píng)審。項(xiàng)目正處于采購(gòu)管理中的哪個(gè)過程?()
    A、實(shí)施采購(gòu)
    B、規(guī)劃采購(gòu)管理
    C、控制采購(gòu)
    D、結(jié)束采購(gòu)

    查看答案

    試題參考答案:A

    試題解析與討論:m.xomuzic.com/st/4878912717.html

  • 試題7

    A team member is responsible for guiding a contractor on a project deliverable.The team member tells the contractor that the deliverable must be redone. The contractor issues a bill fo r the addition work. What should the project manager do 
    一位團(tuán)隊(duì)成員負(fù)責(zé)指導(dǎo)承包商的項(xiàng)目可交付成果相關(guān)工作;該團(tuán)隊(duì)成員告訴承包商部分可交付成果必須返工,承包商簽發(fā)了一份額外工作的賬單。項(xiàng)目經(jīng)理應(yīng)該做什么
    A、Reject the bil1. 拒絕該賬單。
    B、Review the contract. 審查合同。
    C、Share the cost with contractor. 與承包商分?jǐn)偝杀尽?br />D、Add the additional cost to the project budget. 將額外成本添加到項(xiàng)目預(yù)算中。

    查看答案

    試題參考答案:B

    試題解析與討論:m.xomuzic.com/st/479093196.html

  • 試題8

    施工項(xiàng)目經(jīng)理確定,如果延遲一周,進(jìn)度績(jī)效指數(shù)(SP ID)為1.2,成本績(jī)效指數(shù)(CPI)為0.8,項(xiàng)目經(jīng)理在發(fā)生損壞情況時(shí)立即獲得備用設(shè)備。 項(xiàng)目經(jīng)理執(zhí)行的是下列哪一項(xiàng)?
    A、偏差和趨勢(shì)分析
    B、優(yōu)勢(shì)、劣勢(shì)、機(jī)會(huì)與威脅(SWOT)分析
    C、定性和定量風(fēng)險(xiǎn)分析。
    D、預(yù)期貨幣價(jià)值(EMV)分析

    查看答案

    試題參考答案:A

    試題解析與討論:m.xomuzic.com/st/463228909.html

  • 試題9

    A team member informs the project manager that a stakeholder requested limited distribution of progress reports to other stakeholders.What should the project manager do?
    一個(gè)團(tuán)隊(duì)成員通知項(xiàng)目經(jīng)理,一個(gè)相關(guān)方要求向其他相關(guān)方有限制地分發(fā)進(jìn)度報(bào)告項(xiàng)目經(jīng)理應(yīng)該做什么?
    A、Escalate this request to the project sponsor for further review. 將這項(xiàng)請(qǐng)求升級(jí)上報(bào)給項(xiàng)目發(fā)起人進(jìn)講行進(jìn)一步審查。
    B、Explain to the stakeholder that communications management plan must be followe. 向該相關(guān)方解釋必須遵循溝通管理計(jì)劃。
    C、Ask the team member to follow the request,and inform the sponsor. 要求團(tuán)隊(duì)成員遵循這項(xiàng)請(qǐng)求.并通知發(fā)起人。
    D、Have the stakeholder prepare a new project charter that includes this request. 讓該相關(guān)方準(zhǔn)備包含這項(xiàng)請(qǐng)求的新項(xiàng)目章程。

    查看答案

    試題參考答案:B

    試題解析與討論:m.xomuzic.com/st/480609108.html

  • 試題10

    當(dāng)一名關(guān)鍵項(xiàng)目相關(guān)方未能參加所有指導(dǎo)委員會(huì)會(huì)議時(shí),項(xiàng)目經(jīng)理應(yīng)該怎么做?
    A、更新相關(guān)方參與計(jì)劃
    B、將該問題上報(bào)給項(xiàng)目發(fā)起人,并更新風(fēng)險(xiǎn)登記冊(cè)
    C、與關(guān)鍵相關(guān)方開會(huì),協(xié)商并澄清影響
    D、執(zhí)行相關(guān)方分析,確定相關(guān)方的利益影響

    查看答案

    試題參考答案:D

    試題解析與討論:m.xomuzic.com/st/4635522528.html

信管網(wǎng)訂閱號(hào)

信管網(wǎng)視頻號(hào)

信管網(wǎng)抖音號(hào)

溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!

信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。

信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。

相關(guān)內(nèi)容

發(fā)表評(píng)論  查看完整評(píng)論  

報(bào)考條件查詢

推薦文章

精選

課程

提問

評(píng)論

收藏