試題1
一份項(xiàng)目監(jiān)控報(bào)告識別到項(xiàng)目實(shí)施過程中的一個問題,并建議兩個糾正措施。在對監(jiān)控報(bào)告進(jìn)行討論時,項(xiàng)目經(jīng)理發(fā)現(xiàn)該問題是基于不正確的數(shù)據(jù)做出的錯誤結(jié)論。項(xiàng)目經(jīng)理接下來應(yīng)該怎么做?查看答案
試題參考答案:C
試題解析與討論:m.xomuzic.com/st/4930920745.html
試題2
A project's total cost is US$200,000.The project management requests a study to verify whether the project will run behind schedule. The project has a 35% chance of incurring a penalty of US$20,000 due to a delay in completion. There is a 65% chance that the company will earn US$500,000 on the project.查看答案
試題參考答案:C
試題解析與討論:m.xomuzic.com/st/492582292.html
試題3
項(xiàng)目經(jīng)理在與不同層次的不同項(xiàng)目相關(guān)方溝通,項(xiàng)目經(jīng)理現(xiàn)在需要向某一特定項(xiàng)目相關(guān)方發(fā)送一份數(shù)據(jù)報(bào)告。項(xiàng)目經(jīng)理應(yīng)該使用什么溝通方法?查看答案
試題參考答案:B
試題解析與討論:m.xomuzic.com/st/4693220217.html
試題4
項(xiàng)目經(jīng)理和項(xiàng)目團(tuán)隊(duì)在一個偏遠(yuǎn)地區(qū)執(zhí)行項(xiàng)目。在關(guān)鍵階段,一名重要工程資源請求項(xiàng)目經(jīng)理準(zhǔn)許其立即離開現(xiàn)場。項(xiàng)目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:C
試題解析與討論:m.xomuzic.com/st/4692512309.html
試題5
由于產(chǎn)品負(fù)責(zé)人添加了新需求,損害了團(tuán)隊(duì)當(dāng)前的迭代。敏捷管理專業(yè)人士應(yīng)采取什么初步行動?查看答案
試題參考答案:A
試題解析與討論:m.xomuzic.com/st/5308915087.html
試題6
回顧會的主要目的是為了團(tuán)隊(duì):查看答案
試題參考答案:C
試題解析與討論:m.xomuzic.com/st/5296812520.html
試題7
A project manager is lead in a state-of-the art billing system project.The project manager has checked the existing billing system,as well as the lessons learned repository in the company's project management information system(PMIS).The project manager would like to gather more system requirements.What should the project manager do next?查看答案
試題參考答案:B
試題解析與討論:m.xomuzic.com/st/478982970.html
試題8
項(xiàng)目經(jīng)理正在組建一個團(tuán)隊(duì),并希望確保所有成本估算都正確。項(xiàng)目經(jīng)理應(yīng)使用下列哪項(xiàng)工具來確保估算準(zhǔn)確?()查看答案
試題參考答案:B
試題解析與討論:m.xomuzic.com/st/4895119464.html
試題9
Project manager is evaluating the risk associated with possible outcomes of a particular project decision. In this case, it is expected that the decision has a 40% chance of resulting in a loss of $50,000,but a 80% chance of realizing a $200,000 profit.查看答案
試題參考答案:A
試題解析與討論:m.xomuzic.com/st/4910819546.html
試題10
兩位工程師都是各自領(lǐng)域的專家,都被視為珍貴的項(xiàng)目資源,他們存在一起合作的問題。在項(xiàng)目開始時,項(xiàng)目經(jīng)理安排了一次與兩位工程師的會議,制訂沖突的可能解決方案。項(xiàng)目經(jīng)理運(yùn)用的是以下哪種沖突處理方式?查看答案
試題參考答案:A
試題解析與討論:m.xomuzic.com/st/4983414545.html
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |